Friday, October 25, 2013

Water supply


Construction with out water is impossible ,  so here we go with the  next step , getting water from the source with a 2 inch pipe .


The source is around 35 meters above sea level , so we need to carry the main pipe all the way up , well luckily not my job :-)



The water source is inside the cave with a big and deep pool of  fresh water , well the entrance of the cave is quite small but i fit in .






But now we are done and the water is flowing , this pipes is just a temporary set up for the construction time
( we will arrange it properly ones we have the final layout of all structures )