Saturday, January 4, 2014

Truck No. 2 !!!

Finally the truck with cement and steel bar arrive after new year! 600 bags of cement to carry in to the property. ( have fun guys )

 All bags are in the bodega now and save from the rain , but some of our workers are out of order after carrying the cement and steel bar! The guy with the yellow shirt carry 3 bags of cement at once each 20 kg total of 60kg crazy !!


the view from outside :



good bye coconut trees.In the mean time we are busy with the construction we cut the coconut trees inside the property, we really need to because later on they will turn very dangerous to buildings and visitors.


Saturday, December 28, 2013

get ready for the 2nd. floor



preparing for the 2nd. floor.


my turn again for electrical and water



steel bar done in 1 day


concreting the floor . 130 bags of cement



big mess !!!! BUT they did a GREAT GREAT Job... Thanks guys ; )


done and inspection of the boss... Approved well done!!!! 


Friday, December 13, 2013

steel and concreting the first floor


after pluming and electrical , steel matting is next


we finished this very early that day so we are ready for tomorrow to concrete the floor. we bring up the mixer.








Ready !


























Go !





Start at 6:30 am sharp !


done at 1 pm !