Diveshop : after a lot of digging, the foundations are done , but we still need to dig for the retaining wall behind the diveshop and restaurant .
Restaurant/Kitchen/Bar : Steel steel steel ......
after 2 days wiring and pluming .
Done!!!!
ready for the next level .
Friday, June 13, 2014
Thursday, May 15, 2014
Yes , yes , yes GREEN LIGHT !!!!!!!!!!!!!!!!!!!!!!!!!
After long waiting we got all our permits done !!!!!!!! Monday April 28. We started with our project
" BEACH RESORT "
and there we go again ,clearing of the restaurant area :
digging for the foundation
layout for the kitchen!!!
big boss is checking :-)
on the other side, we are still digging for the dive shop endless !!!!!!!!!!
as i said endless digging : right side - new left side - bit older :-)
big rock need to be removed .
temporary roof at the building site
" BEACH RESORT "
and there we go again ,clearing of the restaurant area :
digging for the foundation
layout for the kitchen!!!
big boss is checking :-)
on the other side, we are still digging for the dive shop endless !!!!!!!!!!
as i said endless digging : right side - new left side - bit older :-)
big rock need to be removed .
temporary roof at the building site
Saturday, April 12, 2014
getting ready !!!
Oh no !!!! digging again !!!!!!!!!! we have to remove all the coconut trunks. digging around and chop in small pieces .
A long way to go !!! digging all man power !!!
in the mean time me and savannah checking out the house reef .
it was her first snorkel adventure ever :-) proud daddy !!!!!!
others working already on the steel parts
we need to start around 34 pcs and 6 meters long
and in the kitchen queen is preparing only the best food!!!!!!!
BBQ
Tortilla's
or real german food !!!